Description
Current Situation
- The period is not added if we add two Repeat End-Start periods to the same calendar assigned to job/order with same interval.
How to reproduce
- Create a calendar
- Add the working day calendar to a job or order
- Add the period for to this calendar.
- Use Repeat End-Start with a interval like:
- Begin: 07:00 End: 09:00 and repeat interval is of 00:01.
- Add another Repeat End-Start period to the same calendar like assigned to the job/order:
- Begin: 11:00 End: 12:00 and repeat interval is of 00:01.
- The second period will not be added.
Desired Behavior
- The period should be added even if we add two Repeat End-Start periods to a calendar assigned to job/order with same interval.