Current Behavior:
- When we let run orders from the Daily Plan View, then the orders remain assigned to their original Daily Plan date. However, they will be executed immediately. The "Let run” operation causes the order to start before the beginning of the assigned Daily Plan start time.
- When we select orders and perform the "Let Run" operation on a single order from the Daily Plan view, then all orders currently in the "submitted" state will be executed — not just the selected ones.
Expected Behavior:
- The "Let Run" operation should execute only the selected order(s).
- Other orders in the "submitted" state should remain unaffected unless explicitly selected.